Aleta of Cherryvale, KS on Dec. 23, 2008
June 24, 2008; Tuesday
Sears Estimate Paul
July 3, 2008; Thursday
Measure windows
July 17, 2008, Thursday
Tentative date for windows to be put in ???
August 11, 2008; Monday
Patio door parts scheduled to be received so job of installing windows and doors can start.
August 25, 2008; Monday
Sears to start job of windows and siding. Pulled in with wrong width on insulation. thinner than agreed upon.
Also discovered two living room (after they installed them) windows were not made as agreed upon in our signed contract.
Accepted them as is with Sears gift card after calling Jason. told they couldnt be designed with top opening and top portion being the only portion of the window screened on (oreo) windows.
One bathroom window was not the correct size so installers had to put in a wood shim running vertical of the opening to fill in the space to make window fit.
August 31, 2008; Sunday
Sears finished job of windows and siding
September 3, 2008; Wednesday
Vinyl fascia on back side came off2 pieces plus tore kitchen window screen in the fall
September 18, 2008; Thursday
Suppose to replace fallen fascia??
SundaySears Joe (installer) to come out to replace fascia. Came out with wrong vinyl for the job.
October 10, 2008; Friday
Joe comes to finally replace fallen fascia. He comes while we are working. We were assured by Joe he would check other fascia to prevent possible future problems. He stated in an earlier phone conversation his workers had done the fascia on back side of house and he would check it out to assure no future problems.
Sears Project Coordinator Jason called at our work place and stated Joe would be out at about 3:30 pm. We arrive home from work at 5:30 pm and they were gone by then but fascia was up again.
Tuesday we begin to notice things like our dog had been kicked or hit??took to vet with ribs badly bruised. There was a swollen area somewhat larger than fist size. Vet stuck it with a needle to remove some fluid to acknowledge it was a bad bruise and not something else. It took three weeks for her to heal.
Oct. 20, 2008; Monday
Discovered missing items from garage/pole barn and reported to the police. Over $2,000 of items gone. .10 gallon gas can with gas; electric generator; power saw and large nail gun
Truck parked in pole barn had been gone through apparently looking for key to move it to get air compressor cord and hose free to steal it, but couldnt move the truck so left compressor.
A few days later Jason (Project Coordinator) returned call and gave him the numbers off kitchen screen that had been torn from fascia coming off. No screen yet!!!!
December 13, 2008; Saturday
Called Sears after coming home to many pieces of fascia flapping in the breeze and some had fallen off.
Emailed Paul (Original sales person) pics of some of the house, after calling Sears service number.
Monday husband called Sears.
December 22, 2008; Monday
Timothy to came out and inspected house of our complaints. --took pictures.
December 23, 2008; Tuesday
Timothy called in the morning to send out another Sears installer (REALLY GOOD) to put all fascia up again PROPERLY. I stated we would be at work and had reservations about this given our past experience, but gave in just to get our house looking decent.
It is winter and cold due to be wintery Wednesday so not sure how this will affect installers trying to work.